Create Gantt charts and timeline diagrams with Mermaid for project planning and chronological visualization
Scope: Project timelines, Gantt charts, and chronological visualization with Mermaid.js Lines: ~400 Last Updated: 2025-10-27 Format Version: 1.0 (Atomic)
Activate this skill when:
Simple timeline:
gantt
title Project Timeline
dateFormat YYYY-MM-DD
section Planning
Define Requirements :2024-01-01, 10d
Design Architecture :2024-01-11, 15d
section Development
Build Backend :2024-01-26, 30d
Build Frontend :2024-02-15, 25d
Date format options:
gantt
dateFormat YYYY-MM-DD
%% Also supported: MM-DD, DD, etc.
Task 1 :2024-01-01, 5d
Task 2 :2024-01-06, 1w
Task 3 :2024-01-13, 2w
Active, done, and critical tasks:
gantt
title Development Sprint
dateFormat YYYY-MM-DD
section Backend
API Design :done, api, 2024-01-01, 5d
Database Schema :done, db, 2024-01-06, 3d
API Implementation :active, impl, 2024-01-09, 10d
Testing :test, 2024-01-19, 5d
section Critical Path
Security Review :crit, 2024-01-15, 7d
Deploy to Prod :crit, milestone, 2024-01-24, 0d
Task tags:
done - Completed task (gray)active - Currently in progress (blue)crit - Critical path (red)milestone - Key milestone (marker)Sequential tasks:
gantt
title Task Dependencies
dateFormat YYYY-MM-DD
section Phase 1
Task A :a, 2024-01-01, 5d
Task B :b, after a, 7d
Task C :c, after b, 4d
section Phase 2
Task D :d, after c, 10d
Task E :e, after d, 8d
Multiple dependencies:
gantt
dateFormat YYYY-MM-DD
section Core
Foundation :f, 2024-01-01, 10d
section Parallel
Feature A :a, after f, 15d
Feature B :b, after f, 12d
Feature C :c, after f, 18d
section Integration
Merge All :crit, after a b c, 5d
Project milestones:
gantt
title Product Launch Timeline
dateFormat YYYY-MM-DD
section Q1
Planning :2024-01-01, 30d
MVP Complete :milestone, 2024-01-31, 0d
section Q2
Beta Development :2024-02-01, 60d
Beta Launch :milestone, crit, 2024-04-01, 0d
section Q3
Production Ready :2024-04-02, 90d
Public Launch :milestone, crit, 2024-07-01, 0d
gantt
title Release 2.0 Schedule
dateFormat YYYY-MM-DD
section Planning
Requirements Gathering :done, 2024-01-01, 10d
Technical Design :done, 2024-01-11, 7d
Sprint Planning :done, 2024-01-18, 3d
section Development
Sprint 1 :done, s1, 2024-01-22, 14d
Sprint 2 :active, s2, 2024-02-05, 14d
Sprint 3 :s3, 2024-02-19, 14d
section Testing
QA Testing :after s3, 7d
UAT :after s3, 10d
Security Audit :crit, after s3, 5d
section Deployment
Staging Deploy :milestone, after s3, 0d
Production Deploy :crit, milestone, 2024-03-15, 0d
gantt
title User Authentication Feature
dateFormat YYYY-MM-DD
excludes weekends
section Backend
Database Schema :done, 2024-01-08, 2d
API Endpoints :done, 2024-01-10, 5d
JWT Implementation :active, 2024-01-15, 3d
OAuth Integration :2024-01-18, 5d
section Frontend
Login UI :active, 2024-01-15, 4d
Registration UI :2024-01-19, 3d
Password Reset :2024-01-22, 3d
section Testing
Unit Tests :2024-01-18, 5d
Integration Tests :2024-01-23, 4d
E2E Tests :crit, 2024-01-27, 3d
section Documentation
API Docs :2024-01-25, 3d
User Guide :2024-01-28, 2d
section Milestones
Feature Complete :milestone, crit, 2024-01-31, 0d
gantt
title Cloud Migration Project
dateFormat YYYY-MM-DD
section Preparation
Audit Current Infra :done, 2024-01-01, 14d
Choose Cloud Provider :done, 2024-01-15, 7d
Architecture Design :done, 2024-01-22, 10d
section Migration Phase 1
Setup VPC & Networking :active, p1, 2024-02-01, 7d
Migrate Databases :crit, after p1, 14d
Setup Load Balancers :after p1, 5d
section Migration Phase 2
Migrate App Servers :p2, 2024-02-20, 14d
Configure CDN :after p2, 3d
Setup Monitoring :after p2, 5d
section Testing
Performance Testing :crit, 2024-03-10, 10d
Security Scan :crit, 2024-03-10, 7d
Disaster Recovery Test :crit, 2024-03-17, 5d
section Cutover
DNS Switch :milestone, crit, 2024-03-25, 0d
Decommission Old :2024-03-26, 14d
Simple chronology:
timeline
title History of JavaScript
1995 : Brendan Eich creates JavaScript in 10 days
1997 : ECMAScript 1 released
1999 : ECMAScript 3 released
2005 : AJAX becomes popular
2009 : Node.js released
: ECMAScript 5 released
2015 : ECMAScript 6 (ES2015) major update
2020 : ECMAScript 2020
Multiple events per period:
timeline
title Product Evolution
2020 : MVP Launch
: 1K Users
2021 : Mobile App
: 10K Users
: Series A Funding
2022 : Enterprise Features
: 100K Users
: Profitability
Grouped by era:
timeline
title Company Milestones
section Startup Phase
2019 : Founded
: Seed Funding $1M
2020 : Product Launch
: First 100 customers
section Growth Phase
2021 : Series A $10M
: 1000 customers
: Expand to EU
2022 : Series B $50M
: 10K customers
section Scale Phase
2023 : IPO
: 100K customers
: Global presence
Future planning:
timeline
title Product Roadmap 2024
section Q1
Jan 2024 : Dark Mode
: Mobile App v2.0
Feb 2024 : API v3.0
Mar 2024 : Admin Dashboard
section Q2
Apr 2024 : Multi-language Support
May 2024 : Advanced Analytics
Jun 2024 : Collaboration Features
section Q3
Jul 2024 : Enterprise SSO
Aug 2024 : Audit Logs
Sep 2024 : Custom Workflows
section Q4
Oct 2024 : AI Integrations
Nov 2024 : Mobile SDK
Dec 2024 : Year in Review
timeline
title Frontend Framework Evolution
section Early Web
1995 : JavaScript invented
1999 : XMLHttpRequest (AJAX precursor)
section Library Era
2006 : jQuery released
: Revolutionizes DOM manipulation
2010 : Backbone.js
: First MVC framework for web
section Framework Era
2013 : React introduced by Facebook
2014 : Vue.js released
2016 : Angular 2 rewrite
section Modern Era
2019 : React Hooks
: Vue 3 Composition API
2020 : Svelte gains popularity
2021 : React Server Components
2024 : AI-powered development tools
timeline
title Project XYZ History
section Discovery
Week 1 : Initial brainstorming
: Market research
Week 2 : Competitive analysis
: User interviews
section Design
Week 3 : Wireframes
: User flows
Week 4 : High-fidelity mockups
: Design system
section Development
Week 5-8 : Sprint 1-4
: Core features
Week 9-10 : Testing & QA
section Launch
Week 11 : Beta release
Week 12 : Public launch
: Marketing campaign
timeline
title Professional Journey
section Education
2015-2019 : BS Computer Science
: Internship at Startup
section Early Career
2019-2021 : Junior Developer at Tech Corp
: Learned React, Node.js
: Shipped 3 major features
section Mid Career
2021-2023 : Senior Developer at SaaS Co
: Led team of 4
: Architected microservices
section Current
2023-Present : Tech Lead at Enterprise
: Managing 10 engineers
: Driving technical strategy
Do:
crit tagafter syntaxDon't:
doneDo:
Don't:
gantt
Task A :2024-01-01, 5d
Task B :2024-01-01, 10d %% Should start after A?
✅ Better: Use after for sequential tasks
gantt
Important Task :2024-01-01, 10d
✅ Better: Mark critical tasks
gantt
Important Task :crit, 2024-01-01, 10d
timeline
1990 : Event A
1995 : Event B
Jan 2020 : Event C %% Suddenly very specific
2025 : Event D
✅ Better: Maintain consistent time scale
Use Gantt for:
Use Timeline for:
mermaid-flowcharts.md - Process flowsmermaid-sequence-diagrams.md - Temporal interactionsproject-management.md - Planning methodologies